Muffin Manufacturing Line
Client:
Aryzta Australia
Location:
Sydney, NSW
Scope Overview
Extensive preparation involving removing existing flooring and draining, then installing new floor (in various colours), as well as low barriers for wall protection.
Project Description
The purpose of this project was to upgrade the flooring in preparation for the new muffin manufacturing line going in. A 6mm, hard wearing flooring solution was required to stand up to high volumes of foot and forklift traffic. With machinery being installed shortly after the floor, the timeframe for completion was short.
This project had to be completed over a short weekend period, in time for production on Monday.