New Processing Area

Client:

Australian-Owned Commercial Bakery

Location:

Sydney, NSW

Scope Overview

Extensive preparation involving removing existing flooring and draining, then installing new floor, drainage and low cove.

Project Description

The purpose of this project was to install a new floor in preparation for the new processing line going in. Being a wet-processing line, drainage had to be removed and reconfigured. This project involved extensive preparation, particularly with the drainage, as well as removing the existing flooring and installing our SteriFloor Stärke in light non-slip, B41 Bluebell.

This project had to be completed over a short weekend period, in time for production on Monday.